Caspian Combined Cycle Power Plant

Caspian Combined Cycle Power Plant (Single Shaft) based on building a complete block of combined cycle power plant to support west of Mazandaran needs for electricity near the city of Nowshahr which will be constructed to sale generated electricity. Project investor is Mah-Taab CASPIAN Co. (Affiliated to ARIYAN Mah-Taab GOSTAR group). 

LocationCity of Nowhshahr – Mazandran Province 

Execution Period: Totally 20 months

Tose Sazehaie Energy Khazar has been awarded six contracts from United Energy Developers, EPC contractor of west Mazandaran C.C.P.P., as below:

  • Mobilization and Site preparation of power plant land
  • Main Concrete Structures of the Power Plant (Civil contract No. 1)
  • Main Concrete Structures of the Power Plant (Civil contract No. 2)
  • Manufacturing, Transportation and Erection of Steel Structures
  • Local supply for Innospin Company, Air Cooled Condenser (ACC) 
  • Installation & pre commissioning of firefighting & fire alarm

Please click on picture for related contract